PD
SD
DD
CD
BP
BN
CA
PRE
DESIGN
BUILDING
PERMIT
CONSTRUCTION
DOCUMENTS
DESIGN
DEVELOPMENT
SCHEMATIC
DESIGN
CONSTRUCTION
ADMINISTRATION
BIDDING &
NEGOTATION
2 - 4 WEEKS
4 - 8 WEEKS
8 - 12 WEEKS
8 - 12 WEEKS
12 - 24 WEEKS
3 - 6 WEEKS
THROUGHOUT
CONSTRUCTION
An information gathering phase that will be the foundation for the design phases to follow. The main goal is to learn everything possible about our client's goals and space requirements.
WHAT'S INVOLVED?
​
• background research about site&location
• survey of existing conditions
• determine zoning&land use requirements
• confirm project feasibility/alternatives
• programming
In this phase, we begin the process of translating the Program into an efficient building design. This is when we start exploring design concepts; it is the time for testing options and getting a general idea of the look and feel.
WHAT'S INVOLVED?
​
• sketches & models to test ideas, concepts & relationships
• client feedback & refinements
• preliminary floor plans & exterior concept ready for further development
By the end of this phase, the building exterior will be more fully designed, the interior layout completed, dimensions of all spaces finalized, and most materials selected.
The design drawings are developed into a precise and thorough set of construction documents containing all of the information necessary to communicate the design to a general contractor and build the project.
WHAT'S INVOLVED?
​
• significant advancement and further refinement of the design
• structural engineer & other consultants added to team
• preliminary cost estimating & value engineering
• outline specification
WHAT'S INVOLVED?
​
• client decisions on materials & finishes
• specify all fixtures & components to be installed
• coordination
consultant drawings
• dimensioned drawings & connection details
The construction drawings, along with any additional information required to get a permit are submitted to the
city / jurisdiction for review and approval.
WHAT'S INVOLVED?
​
• building, land use & energy code compliance checklists and forms
• historic district or community design review (if applicable)
• monitor application progress & provide additional information as requested
Some clients already have a contractor in mind when they come to us, but many take advantage of our extensive contractor rolodex and relationships to find their builder and obtain competitive bids.
During construction, the architect's roles advisor to the owner. During this phase we visit the job site at regular intervals to answer questions from the builder and proactively address potential issues.
WHAT'S INVOLVED?
​
• issue drawings and specs to bidding contractors
• answer questions from bidders & issue formal clarifications if necessary
• review & compare bids and advise owner
WHAT'S INVOLVED?
​
•regular on-site meetings with you and your builder
• review pay applications from general contractor & subcontractor shop drawings
• final punch list
PD
SD
DD
CD
BP
BN
CA
PRE
DESIGN
BUILDING
PERMIT
CONSTRUCTION
DOCUMENTS
DESIGN
DEVELOPMENT
SCHEMATIC
DESIGN
CONSTRUCTION
ADMINISTRATION
BIDDING &
NEGOTATION
2 - 4 WEEKS
4 - 8 WEEKS
8 - 12 WEEKS
8 - 12 WEEKS
12 - 24 WEEKS
3 - 6 WEEKS
THROUGHOUT
CONSTRUCTION
An information gathering phase that will be the foundation for the design phases to follow. The main goal is to learn everything possible about our client's goals and space requirements.
WHAT'S INVOLVED?
​
• background research about site&location
• survey of existing conditions
• determine zoning&land use requirements
• confirm project feasibility/alternatives
• programming
In this phase, we begin the process of translating the Program into an efficient building design. This is when we start exploring design concepts; it is the time for testing options and getting a general idea of the look and feel.
WHAT'S INVOLVED?
​
• sketches & models to test ideas, concepts & relationships
• client feedback & refinements
• preliminary floor plans & exterior concept ready for further development
By the end of this phase, the building exterior will be more fully designed, the interior layout completed, dimensions of all spaces finalized, and most materials selected.
The design drawings are developed into a precise and thorough set of construction documents containing all of the information necessary to communicate the design to a general contractor and build the project.
WHAT'S INVOLVED?
​
• significant advancement and further refinement of the design
• structural engineer & other consultants added to team
• preliminary cost estimating & value engineering
• outline specification
WHAT'S INVOLVED?
​
• client decisions on materials & finishes
• specify all fixtures & components to be installed
• coordination
consultant drawings
• dimensioned drawings & connection details
The construction drawings, along with any additional information required to get a permit are submitted to the
city / jurisdiction for review and approval.
WHAT'S INVOLVED?
​
• building, land use & energy code compliance checklists and forms
• historic district or community design review (if applicable)
• monitor application progress & provide additional information as requested
Some clients already have a contractor in mind when they come to us, but many take advantage of our extensive contractor rolodex and relationships to find their builder and obtain competitive bids.
During construction, the architect's roles advisor to the owner. During this phase we visit the job site at regular intervals to answer questions from the builder and proactively address potential issues.
WHAT'S INVOLVED?
​
• issue drawings and specs to bidding contractors
• answer questions from bidders & issue formal clarifications if necessary
• review & compare bids and advise owner
WHAT'S INVOLVED?
​
•regular on-site meetings with you and your builder
• review pay applications from general contractor & subcontractor shop drawings
• final punch list